Construction activities
An activity is an operation or process consuming time and possibly other resources. An individual or work team can manage an activity. It is a measurable element of the total project programme.
The term ‘duration’ refers to the length of time needed to complete an activity.
The term 'path' refers to an activity or an unbroken sequence of activities in a project network. The critical path is the longest sequence of activities through a project network from start to finish, the sum of whose durations determines the overall project duration.
‘Float’ is the time available for an activity in addition to its planned duration. For more information see: Programme float.
‘Free float’ is the amount of time that an activity can be delayed beyond its early start/early finish dates without delaying the early start or early finish of any immediately following activity.
A hanging activity is an activity not linked to any preceding or successor activities.
'Impact' is the effect a change has on an activity or the effect a change to one activity has
on another activity.
Ref Society of Construction Law Delay and Disruption Protocol, 2nd edition, February 2017, published by the Society of Construction Law (UK). https://www.scl.org.uk/resources/delay-disruption-protocol
Earned Value Management Handbook, Published by the Association for Project Management in March 2013 suggests that: ‘…Each work package comprises a number of activities to be performed. Each activity can be assigned to only a single work package. Each activity is a stepping stone towards completion of its parent work package.’
NB The CIOB Planning Protocol 2021 (CIOB PP21), a technical information sheet published by the Chartered Institute of Building (CIOB) in February 2021, defines an activity as: ‘A definable and measurable unit of work. Each activity has a start date, an end date and a duration.’
The glossary of statistical terms, published by the Organisation for Economic Co-operation and Development (OECD), states: ‘An activity is a process, i.e. the combination of actions that result in a certain set of products.’
[edit] Related articles on Designing Buildings
Featured articles and news
New Great British Energy partnership launched
Crown estate help to turbocharge energy independence.
ECA Industry Awards 2024 shortlist revealed
22 leading businesses from across the electrotechnical and engineering services sector.
Government unveils Skills England strategy
Skills England to transform opportunities and drive growth.
New Government Hub for York Given Planning Green Light
For up to 2,600 civil servants, due for completion by 2028.
Construction Skills Certification Scheme cards
July update on Professionally Qualified and Academically Qualified Person Cards.
BSRIA Briefing 2024, November 22
Sustainable Futures: Redefining Retrofit for Net Zero Living.
The CLC on driving competency in the retrofit sector
Previously published roadmap on skills for net zero.
The first labour government King's speech in fifteen years
Construction industry reactions, support and some concern.
CIOB Retrofit of Buildings Technical Information Sheet
What retrofit is, the approach to be taken and processes to be followed.
Adapting Historic Buildings for Energy and Carbon Efficiency
Historic England advice note 18, free download published.
10 retrofit projects revisited 10 years after completion.
Information orders, building liability orders and SPVs
Key BSA terms and how they impact special purpose vehicles.
Listed despite problems with its design.
Zen and the art of cycling exploration.
Design Council Homes Taskforce launched
To support government 1.5 million homes target within UK climate commitments.